The lake is why you bought the lot. It's also why more than one set of rules lands on it. Along Champlain you're dealing with the state's shoreland law, the state's rules for anything in the water, the flood maps, and the town on top of all of them. Here's how they sort out.
The 250 feet
Vermont's Shoreland Protection Act took effect July 1, 2014. It covers land within 250 feet of the mean water level on every lake and pond larger than ten acres, which Champlain is, with room to spare. The state calls that strip the Protected Shoreland Area.
Inside it, creating new cleared area or new impervious surface takes a state permit or a registration. Impervious means hard surface: roofs, and driveways whether they're paved or not.
Everything is measured from the mean water level. Ask the state's shoreland staff which elevation they use for Champlain, and have a surveyor put that line, and the 100 and 250 foot lines behind it, on your plan before anybody designs anything.
What the state looks for
The Act sets standards. A project that meets them has an easier time. One that can't has to add what the state calls best management practices.
- New work set back at least 100 feet from the mean water level, unless the size of the parcel or the site prevents it.
- Built on ground with a slope under 20 percent.
- No more than 20 percent of the protected area in impervious surface.
- No more than 40 percent of it cleared.
- Nothing already standing in the first 100 feet expanded closer to the lake.
Old camps on small lots
Most camp lots were laid out long before any of this, and plenty are too shallow to get anything 100 feet back. The Act allows for that, with a firm line: what's there can't grow toward the water.
A few things need no shoreland permit at all. Rebuilding an existing house, deck or driveway in the exact same footprint is one. Trading one hard surface for another, such as a garage over an existing driveway, is another. So is ordinary upkeep of buildings, lawns and gardens that doesn't enlarge them.
For small projects the state has registrations, which are simpler than a permit. One covers up to 100 square feet of new cleared or hard surface between 25 and 100 feet from the water. Another covers up to 500 square feet between 100 and 250 feet back, provided the parcel meets the slope, impervious and cleared-area standards. Those allowances are counted over the lifetime of the parcel, so an earlier owner may have spent yours.
Trees
Don't cut first and ask after. Within 100 feet of the water, trees come out only under the state's Vegetation Protection Standards, a point system applied to plots 25 feet on a side, where enough trees, saplings and low growth have to stay in each plot. Dead, diseased or unsafe trees may come down if the roots are left in the ground. You may also clear a single footpath to the lake, six feet wide.
Burlington and Colchester handle their own
The state has delegated shoreland permitting to a few municipalities that adopted equivalent rules. On Champlain that means Burlington and Colchester. In those two you go to the municipal office instead of the state. Everywhere else on the lake it's the state, with the town's zoning applying besides.
Anything in the water
Work at or beyond the mean water level falls under a different law and a Lake Encroachment permit. Shoreline stabilization, riprap, fill, and repairs to an existing seawall, concrete dock or boathouse are all on the state's list of examples.
A wooden or metal dock on piles or floats, for noncommercial use, is exempt as long as it doesn't get in the way of boating, stays within the state's limits (a combined 50 feet of horizontal distance and 500 square feet of surface, counting your other structures within 100 feet) and has no concrete, fill or cribwork in it.
Septic, flood, and the town
Installing or replacing a state-permitted wastewater system needs no shoreland permit. The ground it clears still counts toward the parcel's totals.
Flood is a separate question. The state's Flood Ready site has an atlas showing the mapped high-risk zones, and it's blunt on two points: most standard homeowner policies don't cover flood, and a federally backed mortgage on a property in the high-risk zone requires flood insurance. Ask the town what its flood bylaw requires of a new or rebuilt house in that zone.
The town has a say regardless. Shoreline setbacks, lot coverage and height are in the local bylaws and differ from one town to the next. I won't quote them here, because they get amended. The zoning office will tell you what's current for your parcel.
Getting the order right
The state recommends filing a shoreland permit application at least 45 days before you want to start. A registration takes effect 15 days after the state receives it, unless they ask for more information or a full permit.
So it goes survey first, then the rules, then the design. People who draw the house first generally get to draw it twice.
On a lake lot I look at the ground before I talk about what could go there. The water line and the lot lines decide more than the floor plan does.
Is this your project?
This is work I do. See additions for what it covers, or tell me about yours.