A bedroom doesn't have a pipe in it, and in Vermont it's still a plumbing question. The state sizes a septic system by the number of bedrooms in the house. Add one, and you may need a state permit before you can add anything else.
I'm a builder. I don't design septic systems, and the state wants a licensed designer for that work. But this is the step where additions get stopped, so I want you to hear about it early.
Why bedrooms and not bathrooms
The state figures a house's wastewater by how many people could live in it, and it counts people by bedrooms. The rules assume two people for each of the first three bedrooms and one more for every bedroom after that. The number that comes out of that arithmetic is called the design flow.
Bathrooms don't enter into it. The rules say plainly that adding plumbing fixtures to a single-family house is presumed not to raise the design flow. So a second bath on a three-bedroom house is the town's business and the plumber's. A fourth bedroom is the state's.
What the state calls a bedroom
The definition is short: any room in the building that is permitted, used, or serves as sleeping quarters. Notice the word "used." A room labeled "office" on the drawing with a bed in it is a bedroom. So is the bonus room over the garage once somebody sleeps there regular.
I'd rather be straight on the plans than clever. A real office is an office, and nobody will argue. A bedroom drawn as a den tends to come back around when the house is sold and somebody counts rooms against the permit.
When you need the permit
The Wastewater System and Potable Water Supply Rules list what takes a permit. The ones that matter for a remodel or an addition:
- Building a new house, or replacing one.
- Changing an existing building in a way that increases the design flow.
- Changing the use of a building in a way that increases the design flow. The rules count adding bedrooms as a change in use, and going from seasonal to year-round as another.
- Altering or replacing the septic system or the water supply itself.
Starting work early counts against you. The rules treat foundation excavation and site work as the commencement of construction, and that isn't allowed before the permit is issued.
There's an exemption people have heard about and half understand. Houses and systems that were substantially complete before January 1, 2007 don't need a permit just to keep existing. That holds only until you do something on the list above. Adding a bedroom is on the list.
If you're on town sewer
Things are looser, with conditions. Take a single-family house that already has three or more bedrooms, with its own water service line and its own sewer service line running to a municipal treatment plant. For that house the rules presume more bedrooms don't raise the design flow. Other sewered buildings can qualify for an exemption if a designer certifies the service lines can take it and the utility confirms in writing that it has the capacity.
That's a lot of "ifs." Call the regional office and the town's water and sewer department and get the answer for your address.
Who does what
A licensed designer does the design. That's the state's requirement, and it's a separate trade from mine. The designer looks at the existing permit if there is one, evaluates the soil if that's needed, and puts the application together.
The application goes to a regional office of the Department of Environmental Conservation. For Burlington, most of the towns around it, and all of the Islands, that's the Essex office on West Street in Essex Junction. Waterbury goes through the Montpelier office. A few towns have taken over this permitting from the state, and the regional office will point you to the right desk.
What comes back is one of a few answers. The system in the ground may already be permitted for more bedrooms than the house has, and you're set. It may need to be enlarged or replaced, which takes room on the lot and soil that will do the job. Or the lot can't support it, and the plan changes to something without a new bedroom.
Where the builder comes in
After the designer, mostly. I want to know where the tank, the leach field and the well are before I lay out an addition, because the rules set isolation distances between those and any new part of the building. An addition can end up moving ten feet on paper because of a leach field nobody had located.
It matters during the work too. Excavators and concrete trucks don't belong on a leach field. Know where it is and stake it off before the first machine shows up.
So the order is designer first, drawings second, permit in hand third, and then the foundation. People want to do it the other way around because the drawings are the fun part. The septic doesn't care what's fun.