How much concrete to order
Slabs, footings, frost walls and round piers, added into one order and rounded up to the quarter yard. It counts bags too, for the pours too small to call a truck about.
Ten is where I start. Go higher for rough ground, trenches dug with a bucket, or forms you don't trust.
Order 8 cubic yards
| What | Cubic feet | Cubic yards |
|---|---|---|
| Slab 24 by 24 feet, 4 inches thick | 192 | 7.11 |
| All of it, measured | 192 | 7.11 |
| With 10 percent waste | 211.2 | 7.82 |
| Rounded up to the quarter yard | 8 |
In 80 pound bags that would be 352. That's a truck.
Order a little long. A gravel base that sits one inch low under a four inch slab takes a quarter more concrete than the drawing says, and running short with the truck gone leaves a cold joint you will look at for as long as you own the place.
Frost. Footings and piers go below frost, on ground that has never been dug. How deep that is for your town and your soil comes from the town or an engineer, so get the number from them and not from a neighbor. A slab that floats on top is a different design, and somebody has to draw it.
Frozen ground. Don't pour on it. Frozen dirt is holding water as ice, and when it thaws it settles and takes the concrete along. Fresh concrete that freezes before it has cured is damaged for good. Late fall and early spring pours want a forecast, blankets and a plan.
Mud season. Come spring, a good many towns post their gravel roads with weight limits, and a loaded mixer is well over them. If the pour is up a back road, call the town road crew and the plant before you set a date.
What I assumed: square corners, level bottoms and the thickness you gave everywhere. An 80 pound bag is figured at 0.60 cubic feet, so read the bag you buy. This counts volume and nothing else. Slab thickness, footing size, steel and the mix are the plans' business or an engineer's, and the plant rounds its own way. A computer did the adding. Treat it as a rough guide and measure the forms before you call.
What the count is based on
Concrete is sold by the cubic yard, which is 27 cubic feet. A slab is length times width times thickness. A footing or a wall is the same sum under different names. A round pier is the area of the circle times the depth, times however many holes got dug. The calculator turns each one into cubic feet, adds them, puts your waste allowance on top and rounds up to the next quarter yard.
The bag count uses 0.60 cubic feet for an 80 pound bag, which is the yield the common bag makers print. That comes to 45 bags for a single yard, and that tells you most of what you need to know about mixing a garage floor by hand.
What it can’t tell you
How thick the slab should be, how wide the footing, how deep the frost wall or what steel goes in it. Those come off the plans or from an engineer, and the frost depth for your ground comes from the town or the engineer too. I won’t print a depth here and have somebody dig to it.
It can’t see your excavation either. A trench dug by machine is wider than the drawing. Gravel is never as flat as it looks. That is what the waste allowance is for, and on rough ground ten percent is thin.
And it knows nothing about the day. Concrete doesn’t go on frozen ground, a loaded truck may not be allowed up a posted road in mud season, and an October pour takes a different plan than one in July.
If it holds up a building
Then the yardage is the easy part. Send me what you're building and where, and I'll tell you what I'd want to know about the ground before any concrete is ordered.