How to Read a Builder's Estimate

An estimate is a builder telling you what he thinks the job is. Read the words before the numbers, and look hardest for what's been left out.

Planning a build · 4 minute read

An estimate is a builder telling you what he thinks the job is. Most of the fights in this trade start because the owner thought the job was something else. So read the paper slowly, and read the words before the numbers.

Three papers that get confused

An estimate is an educated opinion of what the work will run. A bid or a quote is a price the builder means to stand behind for a described scope. A contract is the signed agreement that binds both of you.

In Vermont the contract is where the law steps in. A residential contractor doing a job valued at $10,000 or more, labor and materials together, has to be registered with the state and has to use a written contract. The Office of Professional Regulation lists what that contract must contain:

  • The price, stated in one of three ways (more on that below).
  • Estimated start and completion dates.
  • A description of the services to be performed and the materials to be used.
  • A change order provision, saying how and when changes get approved and documented. Any amendment has to be in a signed writing.

The state doesn't review anybody's contract for you. Checking that those four things are in there is your job.

Three ways to state a price

The state allows three, and you should know which one you're looking at.

A maximum price for all work and materials. The builder carries the risk of a wrong guess, so he has to know the scope cold, and you should expect that scope to be spelled out tight.

Time and materials, not to exceed a maximum. You pay for hours and materials as they're used, up to a ceiling.

Time and materials with no maximum. This one has an honest use, mostly in old houses where nobody knows what's in the wall until it's open. But understand what you're signing. There is no ceiling unless the paper gives you one.

None of the three is a trick. Trouble comes when the owner believes he has the first kind and the paper says the third.

Read the scope line by line

Look for what's in. Then look harder for what's out. On a new house, the things that commonly sit outside a builder's number include the septic system, the well, the driveway, bringing power to the house, ledge removal, permit fees, appliances and landscaping. On a remodel, look for painting, floor refinishing, and repairs to anything found behind the wall.

Leaving those out isn't wrong. Plenty of them belong to other trades with their own paperwork. What's wrong is when nobody says so and you find out at the end.

If a line reads "install kitchen" and nothing more, ask what kitchen. Good paper names the material: what the siding is, what the windows are, how thick the insulation is, what the floor is made of.

Allowances

An allowance is a placeholder figure for something you haven't picked yet, like light fixtures or tile. They're reasonable. They're also the easiest place to make a total look smaller than it will turn out. Ask what each allowance assumes, then go look at what that amount buys. If your taste runs past it, the difference is yours.

Surprises and change orders

Ask how the paper handles what nobody could see. Ledge in the cellar hole. Rot under a window. Wiring that has to be replaced once it's exposed. A fair estimate says what happens then, and how the added work gets priced.

Every change after signing belongs in writing, signed by both of you, before the work is done. That's the state's rule as well as plain sense. When a wall is opened and I find something, I tell the owner what it is before anything else happens.

Deposits and payments

The state has a rule on down payments. Where the contract carries a maximum price, or time and materials with a cap, it may require a down payment of up to half the cost of labor or half the price of materials, whichever is greater. With uncapped time and materials, the down payment is whatever the two of you negotiate.

The Attorney General's consumer office puts it more bluntly: don't pay all at once. Pay at completion, by installment, or with a reasonable down payment, and keep every invoice.

The City of Burlington's advice to homeowners adds one worth knowing wherever you live. Before the final payment, ask for signed lien releases from the major subcontractors and suppliers, so nobody who went unpaid can come after your house.

Comparing two estimates

Line up the scopes before you look at the bottom lines. The lower number has usually left something out or carried thinner allowances. Ask each builder what the other one included. An honest one will tell you where his own number is soft.

Then ask anybody whose paper you're holding, me included, to walk you through it a line at a time. If he can't explain a line, that line is a problem.

Is this your project?

This is work I do. See additions for what it covers, or tell me about yours.

Thinking about building?

A guide can't see your lot or your house. Tell me where it is and what you want, and I'll come have a look.

(802) 992-8119

Call or text. If I don’t pick up, leave a message and I’ll call you back.

Tell me about the project

A new house, an addition or an old one that needs work. Say what you have and what you want.

This is used to answer you about your project and for nothing else. I’ll call or email you back.

Call Harold Write to me