When this is the right project
- You want a walk-in shower with a tiled floor or a low curb.
- The old fiberglass unit is cracked, or you never liked it.
- A tiled shower already in the house leaks and needs doing over.
- The space is an odd size that no factory unit fits.
Tile doesn't keep water out. Neither does grout. I say that first because most tile showers that leak were built by somebody who believed otherwise.
The layers, from the framing out
- Framing. Studs straight and plumb, blocking where the glass and any bars will fasten, and a floor stiff enough that it won't flex under the tile.
- A sloped pan. The shower floor pitches to the drain, about a quarter inch to the foot by the usual rule. The slope has to be under the waterproofing as well as on top, or water sits in the mortar and goes sour.
- Backer. Cement board or a foam board made for showers. Never plain drywall, and that includes the green kind.
- A membrane. Sheet or brushed on, it runs unbroken across the pan, up the walls, around the curb and into every corner and niche. I'd stick with one maker's system from drain to ceiling. Mixing parts is where trouble starts.
- A flood test. Plug the drain, fill the pan, mark the water line and leave it a full day. If the line hasn't moved, tile can start.
- Tile and grout, with flexible sealant where the walls meet each other and the floor. Grout cracks in a corner. Sealant gives.
Things to decide before the framing closes
The drain can sit in the middle or run as a long slot along one wall. Each needs the floor sloped a different way. A shower with no curb needs the floor framing dropped or the bathroom floor raised, and that's settled at the framing stage or not at all.
Put the valve where you can reach it from outside the spray, so you aren't standing in cold water to turn it on. Place a niche on an inside wall. A bench needs the same waterproofing as the pan and a pitch so water runs off it.
Tile size matters more than people think. Small tile on the floor follows the slope to the drain and gives feet more grout to grip. Big tile on the walls looks clean and shows every bow in the studs, so the walls have to be flat first.
What turns up
When an old shower comes out, the bottom of the wall tells the story. Bottom plates and the ends of the studs gone soft at the curb. Drywall behind the old tile. A drain in cast iron or lead that needs replacing, which is plumbing work. Joists cut for the old trap. That all gets made sound first, since a good membrane over a rotten plate is still a rotten plate.
What to have ready
Have the tile and the valve trim chosen before rough-in. Decide on a door, a fixed glass panel or a curtain, because glass needs blocking in the wall and gets measured after the tile is up. And have another place to shower for a while. The mortar and the sealant need their cure time, and rushing them is how a new shower becomes an old problem.
Showers on outside walls
A shower against an outside wall is two problems in one spot in this climate. The wall is cold, so supply lines and a valve in it can freeze. And the room side of it is wet, so warm damp air pushes toward the framing all winter. If the valve can go on an inside wall, put it there. The outside wall gets insulated full depth and air sealed, and the waterproofing on the shower side has to be unbroken so the wall cavity stays dry. Don't put the niche in that wall. It takes the place of insulation right where you need it most. The fan matters more with a tile shower than with any other kind, because tile and grout hold moisture after the water is off. Duct it outdoors and let it run a while after the shower.
Worth knowing before you start
- Ask whoever builds the shower which waterproofing system they use and whether they flood test the pan. Both answers should come quick.
- Cement board holds up when it's wet. It doesn't stop water. It still needs a membrane.
- Glass is measured after the tile is on the wall, so the door comes a while behind everything else.
- Grout needs cleaning and, depending on the kind, sealing now and then. Ask what you're getting.
Questions I get
How soon can the new shower be used?
When the materials say so. Thinset, grout and sealant all have cure times printed on the bag or the tube, and they run longer in a cold, damp room. Follow them. Using a shower early is one of the few ways an owner can undo good work.
Curb or no curb?
A curb is simpler to build and keeps water in with less fuss. No curb is easier to walk into and better for anyone unsteady on their feet, but the floor framing has to be lowered or the room's floor raised to get the slope. If you think you'll want it someday, build it now. It can't be added later without starting over.
Can tile go over the old tile?
In a shower, I wouldn't. You'd be trusting waterproofing you can't see, built by somebody you never met. Take it down to the studs and know what's there.
Where I build these
Burlington, South Burlington, Shelburne, Williston, Essex, Colchester, Milton, Jericho, Richmond, Waterbury, South Hero and Grand Isle. Each link goes to what bathrooms means in that town.