Most kitchen trouble comes from doing things out of order. The cabinets show up before the floor is ready. The plumber comes back a third time because the sink moved. The countertop gets measured off a drawing instead of off the cabinets. None of it is hard to avoid if the sequence is settled before the first cabinet comes off the wall.
This is the order I'd run it in, and why.
Before anything comes out
Decisions first, all of them. The layout, the cabinets, the sink, the range and the refrigerator all get picked before demolition, because every rough-in is measured off them. A range that changes from 30 inches to 36 after the wiring is in means doing work twice.
Cabinets and appliances get ordered, and nothing gets torn out on a promise. The old kitchen stays in use until the new one is close.
Permits get sorted in this stretch too. What you need depends on the town and on what's being changed.
- Ask the town zoning office whether your job needs a zoning permit. Towns differ on whether inside work takes one.
- In Burlington, a building permit is required for nearly all construction work, with short exceptions like painting and carpeting. The wiring and plumbing take separate trade permits with inspections.
- At the state level, the Division of Fire Safety's permit sheet shows no state construction or electrical permit for work inside a single-family home the owner lives in. Plumbing is different. The sheet says a plumbing permit and a licensed plumber are required when the house is on public water or sewer. Your town may add requirements of its own.
If the house was built before 1978, the Health Department's lead-safe work rules apply to the demolition. That gets planned now, with the rest.
Set up a place to cook somewhere else in the house. Do that last, the night before.
Demolition, and what it shows
Out come the cabinets, counters, flooring and whatever wall surface is going. This is when the house tells you things. The usual finds are a soft subfloor under the sink or the dishwasher, old wiring, and a drain that was never vented right.
When I open a kitchen wall, I tell the owner what's there before anything gets covered back up. Repairs to framing and subfloor happen now. They're simple at this stage and close to impossible once the cabinets are set.
The rough work
The order here is fixed, and for a reason. Big and stiff goes in first, small and flexible last.
- Framing changes: walls moved, openings headered, blocking put in wherever cabinets, shelves or a hood will hang.
- Ductwork for the range hood.
- Plumbing rough-in.
- Electrical rough-in.
- Inspections, where the town or the state calls for them.
- Insulation in any outside wall that's open.
- Drywall, tape and a first coat of paint.
A few of those need a word.
The plumbing and wiring are other people's trades and the job needs both. My part is having the walls ready and the cabinet layout marked on the floor so everybody is working to the same lines.
The range hood should blow outdoors, through the shortest and straightest duct the house allows. Size matters in a way people don't expect. The state energy code handbook says an exhaust hood that can move more than 400 cubic feet a minute has to have makeup air supplied at about the same rate. Without it, a big commercial-style hood in a tight house will pull its air down the chimney. Choose the hood with that in mind.
On insulation, the energy code expects a wall cavity that's been exposed to be filled before it's closed. A kitchen on a north wall with the plaster off is a chance you won't get again for forty years.
Floor, cabinets, counters
I like the finished floor run wall to wall, under the cabinets and the dishwasher. Then the dishwasher can come out someday without a saw, and the next person to change the layout isn't stuck with your footprint. The exception is a floating floor, which has to be free to move and shouldn't be pinned under cabinets.
Cabinets go in level, and the house never is. An old floor can be out an inch across a kitchen. The cabinets get shimmed to a level line, and the gap is dealt with at the toe kick.
Counters are measured after the cabinets are fastened down. Stone and solid tops are templated off the real thing, which means a wait between cabinets and counters. Plan to live with plywood tops and a temporary sink for that stretch.
Finish work
Now the order runs the other way, from the wall out.
- Backsplash, after the counters.
- Plumbing fixtures and the dishwasher hookup.
- Electrical devices, lights and under-cabinet lighting.
- Appliances.
- Trim, hardware, caulk and the last coat of paint.
Then a walk-through with a list. Every door, every drawer, every outlet. Run the dishwasher and look under the sink with a flashlight while it's running.
Where it goes sideways
It's nearly always one of these:
- The layout changes after the rough-in.
- An appliance gets swapped late for one a different size.
- Demolition starts before the cabinets are in hand.
- Nobody put blocking in the wall, and the shelves go where the studs are instead of where you wanted them.
Settle it on paper first. Foot for foot, a kitchen is the most expensive room in the house to build, and the cheapest place to change your mind is on the drawing.