When this is the right project
- The lot is too tight, or the setbacks too close, to build outward.
- You need two or three more rooms, more than a bump-out can give.
- The house is a ranch or a cape on a foundation in good shape.
- The roof is due for replacement anyway.
- You'd give up a quiet summer to keep the yard.
Before I'd talk about what goes upstairs, I'd go down cellar.
Can the house carry it
A second floor is a lot of weight. A first story built to hold up a roof was not always built to hold up a floor, the furniture and people on it, and then a roof with snow on top of that. So the questions start at the bottom.
- The foundation and footings. Sound, plumb and wide enough, or cracked and leaning.
- The first-floor walls. Stud size and spacing, the headers over windows and doors, and whether the load has a straight path to the ground.
- The center beam and posts in the cellar, which pick up the new floor's weight in the middle of the house.
This is a structural engineer's job. I'll say what I see, but the numbers on what an old frame can carry are an engineer's to sign. The fixes they call for (a bigger beam, new posts and footings, heavier headers) get done before anything goes on top.
The stairs take more than you think
A stairway that's safe to use eats a good piece of the first floor, about the size of a small bedroom once you count the landings. Where it goes decides the plan on both floors. People forget this and draw four bedrooms upstairs with nowhere to arrive.
How the work goes
The roof comes off, and for a stretch the house has no lid. That's the nervous part. The new floor deck goes on, walls get stood, and the new roof is framed and dried in as fast as weather allows, with tarps in between. Then windows, siding, and the long inside work: stairs, then wiring, plumbing and heat by those trades, then insulation, drywall and finish.
Most families move out for the roofless part at least. Ceilings downstairs take a beating, plaster especially, and it's fair to plan on redoing some of the first floor too.
The upstairs and the roof are all new, so they get built to today's insulation standards. The old first floor stays what it was unless you open it up, and the house can end up warm upstairs and drafty down. Worth thinking about while the siding is off.
What cutting corners looks like
Skipping the engineer. Stacking a floor on walls nobody checked, then watching the doors downstairs stop closing. Leaving the house open to a week of rain because the lumber was late. And a chimney or plumbing vent that used to clear the roof and now ends in somebody's bedroom, noticed after the framing's done.
Have ready
- Any plans of the house, and its age.
- Photos of the cellar: beam, posts, foundation walls.
- The septic permit, if bedrooms are being added.
- A place to stay.
Height limits, snow and bedrooms
Town zoning sets a height limit, and a second story on a house that already sits close to a lot line can raise questions a first-floor addition wouldn't. Check with the zoning office before paying an engineer. Near the lake, shoreland rules in some towns add another layer. The new roof has to be framed for the snow it will carry, and as a general thing the design snow load climbs with elevation, so a house up a hill road in Underhill or Bolton gets a heavier roof than one down by the water. Rafters or trusses get sized for the place, not out of habit. If the upstairs adds bedrooms and the house is on septic, the state wastewater permit has to cover them. The new story also has to meet the state energy code.
Worth knowing before you start
- Line up the engineer before the design. That report decides what's possible.
- New siding on the whole house often looks better than trying to match forty-year-old clapboards.
- The chimney, the vents and the electrical service all have to be extended or moved. Count them early.
- Time the roofless stretch for dry weather, and have more tarps than you think you need.
Questions I get
Can any house take a second story?
No. Some foundations and frames can carry it as they are, some can with reinforcement, and some would cost so much to shore up that building out or starting over makes more sense. An engineer's look at the cellar and the first-floor framing answers it.
Do I have to move out?
For part of it, plan on it. With the roof off there's no ceiling insulation, the weather is one tarp away, and there are people working over your head. Once the new roof is on and the house is closed in, some folks move back and live with the mess.
Is building up cheaper than building out?
It saves a foundation and it keeps the yard. It adds a stairway, structural work downstairs, a whole new roof and usually repairs to the rooms below. Which comes out ahead depends on the house. Where both are possible, I'd want both priced in writing before you choose.